Cleaning with the Comprex® process
Implementation
- Extensive preliminary planning required due to high complexity
- Mechanical cleaning with compressed, conditioned air from Comprex® unit
- Compressed air supply by Comprex® unit in front of the building
- Access to the system via distributor in the underground garage
- Discharge with decompression box in lifting system
- 3 technicians, 44 day shifts / 9 weeks in operation
Cleaning a heating system in a shopping center
Our services in facts and figures
Comprex® - unit
INDU Sprinter
TECHNICIAN
Project documentation
Result of Comprex® cleaning based on discharge
- Discharge of turbidity, sludge-like deposits and coarse particles from the system
- Efficiency of the heating system restored
- After cleaning, the heating system was filled with water in accordance with VDI 2035 to minimize damage caused by corrosion